PRJ-2026-012On track4ExecutionAgileIn progress

Institutional Performance Measurement & Power BI Dashboards

Add to watchlist

The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.

Budget (BAC)

SAR 490K

Actual cost

SAR 372K

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 490K

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
RC-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2025-02-09⁩
Hijri
10 Shaʻban 1446 AH
ApprovedDMD-2026-012Institutional Performance Measurement & Power BI Dashboards

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-012
Project
Institutional Performance Measurement & Power BI Dashboards
Portfolio
Institutional Excellence & Capability Portfolio
Sector
Strategy & Institutional Excellence
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Tariq S. Al-Yami

1The proposalAuto-filled

TitleAuto-filled
Institutional Performance Measurement & Power BI Dashboards
Proposed byAuto-filled
Tariq S. Al-Yami
DepartmentAuto-filled
Institutional Performance & Quality Department
Submitted onAuto-filled
⁦2025-02-09⁩
Proposal numberAuto-filled
DMD-2026-012

2Justification

The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.

3Objectives

  1. Streamlined governance and dependable technology

Strategic objectives served

  • SO-4.2 — Streamlined governance and dependable technology

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 490K

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 355K
Supervision & consultingSAR 65K
Internal teamSAR 45K
Contingency reserve (5%)SAR 25K
TotalSAR 490K

6Initial risks

RiskLevelProposed response
No initial risks recorded

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Tariq S. Al-YamiHead, Institutional Performance & QualitySubmitted—⁦2025-02-09⁩ 11:08
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2025-02-10⁩ 09:48
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-02-12⁩ 10:55
4Portfolio manager reviewTechnical acceptanceDr. Noura M. Al-OtaibiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2025-02-17⁩ 11:02
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-02-18⁩ 11:44
6Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2025-02-24⁩ 13:16

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2025-02-10⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2025-02-12⁩

Portfolio manager review

Dr. Noura M. Al-Otaibi

Approved⁦2025-02-17⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2025-02-18⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2025-02-24⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Tariq S. Al-Yami on ⁦2025-02-09⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2025-02-10⁩ at ⁦09:48⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-02-12⁩ at ⁦10:55⁩

  3. Technical acceptance

    Portfolio manager review

    Dr. Noura M. Al-Otaibi · Portfolio manager

    Approved · ⁦2025-02-17⁩ at ⁦11:02⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-02-18⁩ at ⁦11:44⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2025-02-24⁩ at ⁦13:16⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-03-02⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Tariq S. Al-Yami

  2. V1Returned for edit⁦2025-02-09⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Tariq S. Al-Yami