PRJ-2026-012On track4ExecutionAgileIn progress

Institutional Performance Measurement & Power BI Dashboards

Add to watchlist

The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.

Budget (BAC)

SAR 490K

Actual cost

SAR 372K

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 490K

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
RC-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2025-09-14⁩
Hijri
22 Rabiʻ I 1447 AH
ApprovedMTG-KO-012Kick-off — Institutional Performance Measurement & Power BI Dashboards

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-012
Project
Institutional Performance Measurement & Power BI Dashboards
Portfolio
Institutional Excellence & Capability Portfolio
Sector
Strategy & Institutional Excellence
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Tariq S. Al-Yami

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Institutional Performance Measurement & Power BI Dashboards
Date and timeAuto-filled
⁦2025-09-14⁩ · 10:00
PlaceAuto-filled
Main meeting room — headquarters
SecretaryAuto-filled
Tariq S. Al-Yami

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Dr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional Excellence
Dr. Amal F. Al-SudairiDirector General, Strategy & the PMO
Tariq S. Al-YamiHead, Institutional Performance & Quality
Dr. Noura M. Al-OtaibiDirector, Project Management Office
Dr. Amal F. Al-SudairiDirector General, Strategy & the PMO

2Roles

PersonRoleDuty
Dr. Mohammed I. Al-SubaieProject sponsorSponsors the project, decides escalations and material changes
Dr. Amal F. Al-SudairiProject ownerApproves the requirements and accepts the deliverables
Tariq S. Al-YamiProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Noura M. Al-OtaibiProject Management OfficeFollows the methodology and checks the periodic updates
Dr. Amal F. Al-SudairiProject ownerDelivers their tasks and uploads the evidence

3Tasks

TaskOwnerDueStatus
Project plan approvedTariq S. Al-Yami⁦2026-01-03⁩Done
Designs approvedTariq S. Al-Yami⁦2026-04-03⁩Done
Build completeTariq S. Al-Yami⁦2026-07-03⁩Done
Testing & acceptance completeTariq S. Al-Yami⁦2026-10-01⁩Open

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Committee: Approves scope, cost and schedule changes (Weekly)
  3. PMO Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-11-23⁩
Start confirmed
Dr. Mohammed I. Al-Subaie · ⁦2025-09-15⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Tariq S. Al-YamiHead, Institutional Performance & QualitySubmitted—⁦2025-09-15⁩ 14:05
2Chair’s approval (sponsor)Technical acceptanceDr. Mohammed I. Al-SubaieProject sponsorApproved—⁦2025-09-16⁩ 12:30
3Minutes against the templateMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-09-17⁩ 12:39

Signatures

Minutes against the template

Ghada A. Al-Shahrani

Approved⁦2025-09-17⁩

Chair’s approval (sponsor)

Dr. Mohammed I. Al-Subaie

Approved⁦2025-09-16⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Tariq S. Al-Yami on ⁦2025-09-15⁩

  1. Methodology review

    Minutes against the template

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-09-17⁩ at ⁦12:39⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Dr. Mohammed I. Al-Subaie · Project sponsor

    Approved · ⁦2025-09-16⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-09-14⁩

    The minutes as taken

    Tariq S. Al-Yami

Only one version so far.