PRJ-2026-014At risk4ExecutionHybridIn progress

My Business Portal 2.0 — the Unified Member Journey

Remove from watchlist

68 member e-services in one journey — membership and renewal, e-attestation, certificates of origin, document verification and appointments — with Nafath sign-in and links to the Ministry of Commerce and the Saudi Business Center.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 4.3M

Actual cost

SAR 2.6M

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SAR 4.5M

SAR +180K

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

My Business Portal 2.0 — the Unified Member Journey

PRJ-2026-014 · Digital Transformation & IT · Strategic · WP-2025-014

In progressAt risk4ExecutionProject manager: Eng. Sultan F. Al-Ghamdi · Sponsor: Eng. Majed S. Al-Rasheed
Progress
⁦58%⁩ / ⁦67%⁩
SPI · CPI
0.87 · 0.96
Spend
SAR 2.6M / SAR 4.3M
Estimate at completion
SAR 4.5M

Schedule

⁦9%⁩ behind⁦58%⁩

Planned to date ⁦67%⁩

Forecast finish: 2027-05-126 Dhuʻl-Hijjah 1448 AH · 42 days late

SPI0.87Schedule performance index · 0.87CPI0.96Cost performance index · 0.96

Health dimensions

At risk

Last update: 2026-10-2716 Jumada I 1448 AH · Up to date

Deliverables

⁦2⁩ of ⁦8⁩ due deliverables accepted on time (⁦25%⁩)

Next milestones

  • Wave 1 development complete (24 services)2026-11-122 Jumada II 1448 AH
  • Nafath & Government Service Bus integration complete2026-12-101 Rajab 1448 AH
  • Penetration test passed, security sign-off2027-01-2820 Shaʻban 1448 AH
  • User acceptance testing complete2027-03-146 Shawwal 1448 AH

Top risks

  • Nafath and Government Service Bus integration interfaces not ready on time16
  • Shortage of integration and back-end engineers on the vendor team16
  • Late sign-off of membership and attestation requirements by the owning departments12
  • Possible critical findings in the pre-launch penetration test12

Open impediments

  • Shared Nafath test environment down for 9 days · Escalated
  • Vendor late delivering updated Government Service Bus interface specs · Open
  • Two vendor integration engineers withdrawn with no replacement · Overdue

Decisions and changes waiting

  • Review the returned data migration plan
  • Replacement plan for the vendor integration engineers
  • Access request: integration adviser on the My Business Portal 2.0 project
  • CR-2026-004 · Add membership transfer & record merge to the first release

Copilot summary

The project is 58% complete against 67% planned (SPI 0.87) and is forecast to finish on 12 May 2027 instead of 31 March 2027 — 42 days late. The slip sits in national-systems and agency integration (41% done) and the “Wave 1 complete” milestone, which missed 30 September and is now forecast for 12 November.

Three main causes: (1) the shared Nafath test environment was down for 9 days; (2) two vendor integration engineers left with no replacement — an impediment now overdue; (3) internal resource strain — the lead integration engineer is at 135% and shared with the mobile app. The membership-data migration plan was also returned for rework.

Riyadh Chamber of Commerce & Industry · prepared by Eng. Sultan F. Al-Ghamdi in MunjazInternal

Status: At risk ·Project page