Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-014At risk4ExecutionHybridIn progress

My Business Portal 2.0 — the Unified Member Journey

Remove from watchlist

68 member e-services in one journey — membership and renewal, e-attestation, certificates of origin, document verification and appointments — with Nafath sign-in and links to the Ministry of Commerce and the Saudi Business Center.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 4.3M

Actual cost

SAR 2.6M

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SAR 4.5M

SAR +180K

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
RC-PMO-F09
Template edition
3.1
Version
V1
Form date
⁦2026-10-15⁩
Hijri
4 Jumada I 1448 AH
In approvalCR-2026-004Add membership transfer & record merge to the first release

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-014
Project
My Business Portal 2.0 — the Unified Member Journey
Portfolio
Member Services & Business Voice Portfolio
Sector
Digital Transformation & IT
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Eng. Sultan F. Al-Ghamdi

1The change

TitleAuto-filled
Add membership transfer & record merge to the first release
KindAuto-filled
Scope
Requested byAuto-filled
Eng. Reem K. Al-Dosari
Raised onAuto-filled
⁦2026-10-15⁩

Reason

The membership & attestation directorate asked to bring membership transfer and record merge into the first release

Justification

About 3,200 transfer and merge requests come in a month; leaving the service for wave 2 keeps them on paper six more months and loads the Premium Members Centre and the branches

2Impact analysis

Cost

SAR +92.5K

Schedule

+21 days

Risk

12 → 15

Benefits

+7%

Risk impact

Adds requirements the membership department and the branches must sign, and loads the integration team

Benefits impact

3,200 transfer and merge requests a month digitised six months early

3The approval decision

The PMO’s recommendation

The PMO recommends conditional approval: add the service once the Government Service Bus integration is done, and win back part of the days through CR-2026-012

Change Committee decision
Not taken yet
Decided on
—
Decision number
—

Conditions

  • The service does not start before the Government Service Bus integration is complete
  • Approve CR-2026-012 to add integration capacity

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Reem K. Al-DosariHead of the My Business Portal & Programme Manager, Digital Member JourneySubmitted—⁦2026-10-15⁩ 13:40
2Project managerTechnical acceptanceEng. Sultan F. Al-GhamdiProject managerApproved—⁦2026-10-18⁩ 09:24
3PMO review & impact analysisMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-10-20⁩ 10:31
4Financial impactFinancial approvalApproval engineFinancePre-breach alert—⁦2026-10-22⁩ 08:00

Signatures

Project manager

Eng. Sultan F. Al-Ghamdi

Approved⁦2026-10-18⁩

PMO review & impact analysis

Ghada A. Al-Shahrani

Approved⁦2026-10-20⁩

Financial impact

Munirah A. Al-Khalidi

Awaiting decision

Contractual impact

Mazen A. Al-Hazmi

Later

Change Committee

Dr. Mohammed I. Al-Subaie

Later

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F09 · version V1

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. Reem K. Al-Dosari on ⁦2026-10-15⁩

  1. Technical acceptance

    Project manager

    Eng. Sultan F. Al-Ghamdi · Project manager

    Approved · ⁦2026-10-18⁩ at ⁦09:24⁩

  2. Methodology review

    PMO review & impact analysis

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-10-20⁩ at ⁦10:31⁩

  3. Financial approval

    Financial impact

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    4 working days overdueAction time limit exceeded · Limit 2 working daysLimit 2 working days · Due ⁦2026-10-22⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-22⁩

    Waiting on Khalid N. Al-Mutairi
  4. Financial approval

    Contractual impact

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Limit 2 working days · Expected by ⁦2026-10-26⁩

  5. Technical acceptance

    Change Committee

    Dr. Mohammed I. Al-Subaie · Change Committee

    Delegated to Dr. Noura M. Al-Otaibi

    Limit 3 working days · Expected by ⁦2026-10-29⁩

Steps that do not apply to this record

  • Projects Steering Committee — the condition «Cost impact above the Change Committee’s authority?» does not holdFrom the authority matrix
  • Executive Committee — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-10-15⁩

    The request as raised

    Eng. Reem K. Al-Dosari

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close