Budget (BAC)
Actual cost
60% of budget
Progress
Estimate at completion
SAR +180K
SPI · CPI
Forecast finish
42 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure31 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Charter approvedMS-01 | Executive | 2025-01-05 | 2025-01-05 | On time | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Achieved | 1 | Approved |
| Build & run contract signedMS-02 | Contractual | 2025-04-30 | 2025-05-04 | +4 days | Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@chamber.sa | Achieved | 2 | Approved |
| Advance payment (10%) releasedMS-03 | Payment | 2025-05-25 | 2025-06-01 | +7 days | Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@chamber.sa | Achieved | 2 | Approved |
| Requirements & design signed offMS-04 | Project | 2025-09-30 | 2025-10-21 | +21 days | Lama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Member ServicesP-006l.alharbi@chamber.sa | Achieved | 2 | Approved |
| Internal pilot (MVP) liveMS-05 | Project | 2026-03-31 | 2026-04-28 | +28 days | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, My Business Portal 2.0P-005s.alghamdi@chamber.sa | Achieved | 2 | Approved |
| Data classification approved by the data officeMS-06 | Regulatory | 2026-06-30 | 2026-07-14 | +14 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@chamber.sa | Achieved | 1 | Approved |
| Wave 1 development complete (24 services)MS-07 | Contractual | 2026-09-30 | 2026-11-12 | +43 days | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, My Business Portal 2.0P-005s.alghamdi@chamber.sa | Late | 1 | Not requested |
| Nafath & Government Service Bus integration completeMS-08 | Project | 2026-10-31 | 2026-12-10 | +40 days | Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030h.alqurashi@chamber.sa | At risk | 0 | Not requested |
| Penetration test passed, security sign-offMS-09 | Regulatory | 2026-12-15 | 2027-01-28 | +44 days | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@chamber.sa | At risk | 0 | Not requested |
| User acceptance testing completeMS-10 | Project | 2027-01-31 | 2027-03-14 | +42 days | Joud N. Al-AhmadiJoud N. Al-AhmadiQA & Testing SpecialistP-033j.alahmadi@chamber.sa | At risk | 0 | Not requested |
| Official launch of My Business Portal 2.0MS-11 | Executive | 2027-03-01 | 2027-04-15 | +45 days | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | At risk | 0 | Not requested |
| Final acceptance & final paymentMS-12 | Payment | 2027-03-31 | 2027-05-12 | +42 days | Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@chamber.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
58%Awaiting acceptance
23%Not handed in
19%Deliverable flow
Display options
| Business requirements documentDLV-01 | 10% | CRT-014-01 | Approved | Lama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Member ServicesP-006l.alharbi@chamber.sa | Eng. Reem K. Al-Dosari | 2025-08-31 | V4 | 3 of 3 |
| UX prototypeDLV-02 | 6% | CRT-014-02 | Approved | Maha F. Al-KhathamiMaha F. Al-KhathamiFront-end Developer (Contractor)P-044m.alkhathami@chamber.sa | Lama S. Al-Harbi | 2025-09-15 | V3 | 3 of 3 |
| Solution & integration designDLV-03 | 6% | — | Under review | Eng. Asma S. Al-HamdanEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@chamber.sa | Eng. Laila Mansour | 2026-10-15 | V5 | 2 of 4 |
| Wave 1 service package (24 services)DLV-04 | 14% | — | Submitted | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, My Business Portal 2.0P-005s.alghamdi@chamber.sa | Joud N. Al-Ahmadi | 2026-09-30 | V1 | 1 of 3 |
| Nafath integration interfacesDLV-05 | 5% | — | Draft | Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030h.alqurashi@chamber.sa | Eng. Yasser M. Al-Zahrani | 2026-10-31 | V2 | 1 of 3 |
| Government Service Bus integration interfacesDLV-06 | 5% | — | Draft | Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030h.alqurashi@chamber.sa | Yousef A. Al-Omari | 2026-11-15 | V1 | 0 of 3 |
| Data migration planDLV-07 | 3% | — | Returned | Rakan F. Al-MohammadiRakan F. Al-MohammadiData EngineerP-032r.almohammadi@chamber.sa | Eng. Asma S. Al-Hamdan | 2026-10-10 | V2 | 1 of 3 |
| Master test planDLV-08 | 4% | CRT-014-08 | Approved | Joud N. Al-AhmadiJoud N. Al-AhmadiQA & Testing SpecialistP-033j.alahmadi@chamber.sa | Eng. Sultan F. Al-Ghamdi | 2026-06-30 | V3 | 3 of 3 |
| Performance & load test reportDLV-09 | 3% | — | Draft | Eng. Saad M. Al-DosariEng. Saad M. Al-DosariCloud & Integration EngineerP-034sa.aldosari@chamber.sa | Eng. Asma S. Al-Hamdan | 2026-12-20 | V0 | 0 of 2 |
| Change management & training planDLV-10 | 3% | — | Submitted | Nouf M. Al-BalawiNouf M. Al-BalawiChange Management SpecialistP-035n.albalawi@chamber.sa | Eng. Reem K. Al-Dosari | 2026-10-31 | V2 | 3 of 3 |
| User & operator guideDLV-11 | 3% | — | Draft | Lama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Member ServicesP-006l.alharbi@chamber.sa | Nouf M. Al-Balawi | 2027-02-15 | V0 | 0 of 2 |
| Internal pilot: the core platform and three servicesDLV-12 | 30% | CRT-014-12 | Approved | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, My Business Portal 2.0P-005s.alghamdi@chamber.sa | Eng. Reem K. Al-Dosari | 2026-03-31 | V2 | 3 of 3 |
| Approved service-data classification registerDLV-13 | 8% | CRT-014-13 | Approved | Rakan F. Al-MohammadiRakan F. Al-MohammadiData EngineerP-032r.almohammadi@chamber.sa | Rahaf I. Al-Nefaie | 2026-06-30 | V2 | 3 of 3 |
| Total · 13 | 100% |