PRJ-2026-021On track3PlanningConstructionNot started
Chamber Conference & Exhibition Hall — Phase 1
Add to watchlistA 3,000-seat multi-purpose hall for the Riyadh Economic Forum, the annual ceremony and the “Muntijoon” exhibition, ready for Expo 2030 events; now at tender.
Project managerEng. Ibrahim A. Al-GhamdiProject sponsorSarah A. Al-QarniProgrammeNew Headquarters & Investment Assets Programme
Budget (BAC)
SAR 26M
Actual cost
SAR 520K
2% of budget
Progress
2%Awaiting acceptance 0%
Estimate at completion
SAR 26M
SPI · CPI
1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Forecast finish
2028-12-31
On baseline
PlanningStage 3 of 5
Next gate:Execution12 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started