PRJ-2026-021On track3PlanningConstructionNot started

Chamber Conference & Exhibition Hall — Phase 1

Add to watchlist

A 3,000-seat multi-purpose hall for the Riyadh Economic Forum, the annual ceremony and the “Muntijoon” exhibition, ready for Expo 2030 events; now at tender.

Budget (BAC)

SAR 26M

Actual cost

SAR 520K

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 26M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution12 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Periodic update cards

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Period

October 2026

Draft
Progress
⁦2%⁩
Planned
⁦2%⁩
SPI
1.00
Open the card

Periodic update cards

PeriodStatusProgressCurrent stepDate
October 2026UPD-021-2026-10Draft⁦2%⁩—⁦2026-10-26⁩
September 2026UPD-021-2026-09Approved⁦0%⁩—⁦2026-10-02⁩
August 2026UPD-021-2026-08Approved⁦0%⁩—⁦2026-09-02⁩