Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-021On track3PlanningConstructionNot started

Chamber Conference & Exhibition Hall — Phase 1

Add to watchlist

A 3,000-seat multi-purpose hall for the Riyadh Economic Forum, the annual ceremony and the “Muntijoon” exhibition, ready for Expo 2030 events; now at tender.

Budget (BAC)

SAR 26M

Actual cost

SAR 520K

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 26M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution12 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
RC-PMO-F05
Template edition
2.0
Version
V1
Form date
⁦2026-04-30⁩
Hijri
13 Dhuʻl-Qiʻdah 1447 AH
In approvalPRJ-2026-021Chamber Conference & Exhibition Hall — Phase 1

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-021
Project
Chamber Conference & Exhibition Hall — Phase 1
Portfolio
New Headquarters & Investment Assets Portfolio
Sector
Events & Trade Delegations
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Ibrahim A. Al-Ghamdi

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2026-04-05⁩

Baseline finish

⁦2028-12-31⁩

Forecast finish

⁦2028-12-31⁩

SPI

1.00

MilestonePlannedForecastSlip
Project plan approved⁦2026-10-29⁩⁦2027-02-16⁩+110 days
Designs approved⁦2027-04-05⁩⁦2027-07-04⁩+90 days
Build complete⁦2027-11-30⁩⁦2028-01-27⁩+58 days
Testing & acceptance complete⁦2028-07-25⁩⁦2028-08-21⁩+27 days
Final handover⁦2028-12-31⁩⁦2029-01-06⁩+6 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦2%⁩⁦2026-08-10⁩Eng. Ibrahim A. Al-Ghamdi
Monitoring & reporting⁦3%⁩⁦2026-10-29⁩Yousef A. Al-Omari
Detailed design⁦6%⁩⁦2027-01-16⁩Yousef A. Al-Omari
Permits & approvals⁦6%⁩⁦2027-04-05⁩Sarah A. Al-Qarni
Site works & excavation⁦13%⁩⁦2027-06-24⁩Sarah A. Al-Qarni
Structure⁦13%⁩⁦2027-09-11⁩Eng. Ibrahim A. Al-Ghamdi
Finishes⁦13%⁩⁦2027-11-30⁩Yousef A. Al-Omari
Supply⁦10%⁩⁦2028-02-17⁩Eng. Ibrahim A. Al-Ghamdi
Installation⁦10%⁩⁦2028-05-07⁩Yousef A. Al-Omari
Testing & commissioning⁦10%⁩⁦2028-07-25⁩Sarah A. Al-Qarni
Provisional acceptance⁦7%⁩⁦2028-10-13⁩Yousef A. Al-Omari
Final acceptance⁦7%⁩⁦2028-12-31⁩Sarah A. Al-Qarni
Accepted with a certificate⁦2%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0046Tender prices 18% above the engineer’s estimate15MitigateEng. Ibrahim A. Al-Ghamdi

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Ibrahim A. Al-Ghamdi
Project ownerDeliverable status and acceptance datesFortnightlyEng. Ibrahim A. Al-Ghamdi
PMOData and indicator updatesWeeklyEng. Ibrahim A. Al-Ghamdi
BeneficiariesWhat changes and whenAt each milestoneEng. Ibrahim A. Al-Ghamdi
Team memberRoleAllocation
Eng. Ibrahim A. Al-GhamdiProject manager (tender stage)⁦30%⁩
Yousef A. Al-OmariBeneficiary lead — conference & exhibition hall requirements⁦25%⁩
Mazen A. Al-HazmiConference & exhibition hall tender⁦30%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsSubmitted—⁦2026-10-23⁩ 13:10
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-10-25⁩ 09:42
3Technical acceptance — project ownerTechnical acceptanceApproval engineProject ownerPre-breach alert—⁦2026-10-28⁩ 08:00

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2026-10-25⁩

Technical acceptance — project owner

Yousef A. Al-Omari

Awaiting decision

Cash flow & financial commitment

Munirah A. Al-Khalidi

Later

Sponsor approval

Sarah A. Al-Qarni

Later

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F05 · version V1

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Ibrahim A. Al-Ghamdi on ⁦2026-10-23⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-10-25⁩ at ⁦09:42⁩

  2. Technical acceptance

    Technical acceptance — project owner

    Yousef A. Al-Omari · Project owner
    Due todayAction time limit about to lapse · Limit 3 working daysLimit 3 working days · Due ⁦2026-10-28⁩

    Pre-breach alert at ⁦70%⁩ — sent ⁦2026-10-28⁩

    Waiting on Yousef A. Al-Omari
  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    Limit 2 working days · Expected by ⁦2026-11-01⁩

  4. Technical acceptance

    Sponsor approval

    Sarah A. Al-Qarni · Project sponsor

    Limit 3 working days · Expected by ⁦2026-11-04⁩

Steps that do not apply to this record

  • Plan aligned with the contracts — the condition «Contract link?» does not hold

Previous versions

Every version is kept with its status and what changed.

  1. V2In approval⁦2026-04-30⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Ibrahim A. Al-Ghamdi

  2. V1Returned for editCurrent⁦2026-04-16⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Ibrahim A. Al-Ghamdi

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close