Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-021On track3PlanningConstructionNot started

Chamber Conference & Exhibition Hall — Phase 1

Add to watchlist

A 3,000-seat multi-purpose hall for the Riyadh Economic Forum, the annual ceremony and the “Muntijoon” exhibition, ready for Expo 2030 events; now at tender.

Budget (BAC)

SAR 26M

Actual cost

SAR 520K

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 26M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution12 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Fields required by the project’s stage (Planning): 15 fields required now.Field settings

Riyadh Chamber of Commerce & Industry

Project charter

Chamber Conference & Exhibition Hall — Phase 1

APPROVEDV2Approved ⁦2026-04-03⁩

1Project identity

Required at this stage
Project name
Chamber Conference & Exhibition Hall — Phase 1
Project code
PRJ-2026-021
Project sponsor
Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa
Project manager
Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa
Project owner
Yousef A. Al-OmariYousef A. Al-OmariExecutive Director, Events & Trade DelegationsP-016y.alomari@chamber.sa
Portfolio & programme
New Headquarters & Investment Assets PortfolioNew Headquarters & Investment Assets Programme
Type & methodology
Infrastructure · Construction
Current phase
3Planning

2Background & rationale

Required at this stage

A ⁦3,000-seat multi-purpose hall for the Riyadh Economic Forum⁩, the annual ceremony and the “Muntijoon” exhibition, ⁦ready for Expo 2030 events⁩; now at tender.

3Objectives

Required at this stage
  1. 1A stronger presence in forums, events and trade delegations
  2. 2Financial sustainability

4Scope

Required at this stage

In scope

  • A ⁦3,000-seat multi-purpose hall for the Riyadh Economic Forum⁩, the annual ceremony and the “Muntijoon” exhibition, ⁦ready for Expo 2030 events⁩; now at tender.
  • Saudi Building Code compliance
  • An approved plan to keep member services and training running during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Saudi Building Code compliance
  2. 2An approved plan to keep member services and training running during the works
  3. 3Civil-defence requirements

6Deliverables

Required at this stage
1Project management plan⁦2026-05-15⁩
2Main deliverable — stage 1⁦2027-08-29⁩
3Main deliverable — final stage⁦2028-08-13⁩
4Final report⁦2028-12-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2026-04-03⁩
  2. Contract signed⁦2026-09-12⁩
  3. 50% of works complete⁦2027-08-29⁩
  4. Provisional acceptance⁦2028-10-12⁩
  5. Closure⁦2028-12-31⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩18.7M
  • Supervision & consulting⁦14.0%⁩3.6M
  • Internal team⁦9.0%⁩2.3M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩1.3M
The owning sector’s approved budgetTotal26M

9Timeline

Required at this stage
Start
2026-04-0517 Shawwal 1447 AH
Baseline finish
2028-12-3115 Shaʻban 1450 AH
Duration
⁦33⁩ months

10Key risks

Required at this stage
  • High⁦Tender prices 18% above the engineer⁩’s estimate

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly