Chamber Conference & Exhibition Hall — Phase 1
Add to watchlistA 3,000-seat multi-purpose hall for the Riyadh Economic Forum, the annual ceremony and the “Muntijoon” exhibition, ready for Expo 2030 events; now at tender.
Budget (BAC)
Actual cost
2% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningStage 3 of 5
Next gate:Execution12 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-10-29 | 2027-02-16 | +110 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-04-05 | 2027-07-04 | +90 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-11-30 | 2028-01-27 | +58 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | At risk | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2028-07-25 | 2028-08-21 | +27 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2028-12-31 | 2029-01-06 | +6 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
2%Awaiting acceptance
0%Not handed in
98%Deliverable flow
Display options
| Project plan & baseline021-D1 | 2% | CRT-021-01 | Approved | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | Yousef A. Al-Omari | 2026-08-10 | V1 | 3 of 3 |
| Monitoring & reporting021-D2 | 3% | — | Draft | Yousef A. Al-OmariYousef A. Al-OmariExecutive Director, Events & Trade DelegationsP-016y.alomari@chamber.sa | Yousef A. Al-Omari | 2026-10-29 | V0 | 0 of 3 |
| Detailed design021-D3 | 6% | — | Draft | Yousef A. Al-OmariYousef A. Al-OmariExecutive Director, Events & Trade DelegationsP-016y.alomari@chamber.sa | Yousef A. Al-Omari | 2027-01-16 | V0 | 0 of 3 |
| Permits & approvals021-D4 | 6% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Yousef A. Al-Omari | 2027-04-05 | V0 | 0 of 3 |
| Site works & excavation021-D5 | 13% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Yousef A. Al-Omari | 2027-06-24 | V0 | 0 of 3 |
| Structure021-D6 | 13% | — | Draft | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | Yousef A. Al-Omari | 2027-09-11 | V0 | 0 of 3 |
| Finishes021-D7 | 13% | — | Draft | Yousef A. Al-OmariYousef A. Al-OmariExecutive Director, Events & Trade DelegationsP-016y.alomari@chamber.sa | Yousef A. Al-Omari | 2027-11-30 | V0 | 0 of 3 |
| Supply021-D8 | 10% | — | Draft | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision of Construction ProjectsP-036i.alghamdi@chamber.sa | Yousef A. Al-Omari | 2028-02-17 | V0 | 0 of 3 |
| Installation021-D9 | 10% | — | Draft | Yousef A. Al-OmariYousef A. Al-OmariExecutive Director, Events & Trade DelegationsP-016y.alomari@chamber.sa | Yousef A. Al-Omari | 2028-05-07 | V0 | 0 of 3 |
| Testing & commissioning021-D10 | 10% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Yousef A. Al-Omari | 2028-07-25 | V0 | 0 of 3 |
| Provisional acceptance021-D11 | 7% | — | Draft | Yousef A. Al-OmariYousef A. Al-OmariExecutive Director, Events & Trade DelegationsP-016y.alomari@chamber.sa | Yousef A. Al-Omari | 2028-10-13 | V0 | 0 of 3 |
| Final acceptance021-D12 | 7% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Yousef A. Al-Omari | 2028-12-31 | V0 | 0 of 3 |
| Total · 12 | 100% |