Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-023On track2InitiationAgileNot started

Sectoral Committee Recommendations Tracker

Add to watchlist

Follow every recommendation from its sectoral committee to the government body concerned until it is decided, with a dashboard for the board and committee members.

Budget (BAC)

SAR 1.4M

Actual cost

SAR 14K

⁦1%⁩ of budget

Progress

⁦1%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 1.4M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

InitiationStage ⁦2⁩ of ⁦5⁩

Next gate:Planning6 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current stageInitiation · Current stage
  3. Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
  4. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
RC-PMO-F04
Template edition
3.0
Version
V1
Form date
⁦2026-10-19⁩
Hijri
8 Jumada I 1448 AH
In approvalPRJ-2026-023Sectoral Committee Recommendations Tracker

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-023
Project
Sectoral Committee Recommendations Tracker
Portfolio
Member Services & Business Voice Portfolio
Sector
Business Support Sector
Sponsor
Eng. Ziyad A. Al-Dakheel
Project manager
Rahaf I. Al-Nefaie

1Objective

Background

Follow every recommendation from its sectoral committee to the government body concerned until it is decided, with a dashboard for the board and committee members.

Project objectives

  1. Greater influence on government decision-making
  2. Active sectoral committees and business challenges resolved

2Scope

In scope

  • Follow every recommendation from its sectoral committee to the government body concerned until it is decided, with a dashboard for the board and committee members.
  • Single sign-on through Nafath
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2026-09-25⁩
Main deliverable — stage 1⁦2027-05-10⁩
Main deliverable — final stage⁦2027-10-25⁩
Final report⁦2027-12-31⁩
MilestoneDate
Charter approved⁦2026-09-04⁩
Contract signed⁦2026-11-22⁩
50% of works complete⁦2027-05-10⁩
Provisional acceptance⁦2027-11-23⁩
Closure⁦2027-12-31⁩

4RolesAuto-filled

SponsorAuto-filled
Eng. Ziyad A. Al-Dakheel
Project ownerAuto-filled
Hala F. Al-Angari
Project managerAuto-filled
Rahaf I. Al-Nefaie
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSAR 1M
Supervision & consultingSAR 195K
Internal teamSAR 125K
Contingency reserve (5%)SAR 70K
Approved budgetSAR 1.4M

Funding

The owning sector’s approved budget

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Rahaf I. Al-NefaieDirector, Data & AISubmitted—⁦2026-10-19⁩ 10:00
2PMO complianceMethodology reviewApproval enginePMO — directorPre-breach alert—⁦2026-10-22⁩ 08:00
3PMO complianceMethodology reviewApproval engineEscalated automatically to Senior management (Dr. Abdullah S. Al-Qahtani) on ⁦2026-10-27⁩Automatic escalation—⁦2026-10-27⁩ 08:05

Signatures

PMO compliance

Dr. Noura M. Al-Otaibi

Awaiting decision

Project owner

Hala F. Al-Angari

Later

Budget funding confirmed

Munirah A. Al-Khalidi

Later

Sponsor approval

Eng. Ziyad A. Al-Dakheel

Later

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F04 · version V1

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Rahaf I. Al-Nefaie on ⁦2026-10-19⁩

  1. Methodology review

    PMO compliance

    Dr. Noura M. Al-Otaibi · PMO — director
    4 working days overdueAction time limit exceeded · Limit 3 working daysLimit 3 working days · Due ⁦2026-10-22⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-22⁩

    Escalated automatically to Senior management (Dr. Abdullah S. Al-Qahtani) on ⁦2026-10-27⁩

  2. Technical acceptance

    Project owner

    Hala F. Al-Angari · Project owner

    Limit 3 working days · Expected by ⁦2026-10-27⁩

  3. Financial approval

    Budget funding confirmed

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    Limit 2 working days · Expected by ⁦2026-10-29⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Ziyad A. Al-Dakheel · Project sponsor

    Limit 3 working days · Expected by ⁦2026-11-03⁩

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-10-19⁩

    Submitted for approval

    • First complete version

    Rahaf I. Al-Nefaie

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close