PRJ-2026-023On track2InitiationAgileNot started

Sectoral Committee Recommendations Tracker

Add to watchlist

Follow every recommendation from its sectoral committee to the government body concerned until it is decided, with a dashboard for the board and committee members.

Budget (BAC)

SAR 1.4M

Actual cost

SAR 14K

⁦1%⁩ of budget

Progress

⁦1%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 1.4M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

InitiationStage ⁦2⁩ of ⁦5⁩

Next gate:Planning6 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current stageInitiation · Current stage
  3. Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
  4. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work1.4M⁦16⁩ elements
Unallocated contingency42KSAR 70K
Budget at completion1.4MPRJ-2026-023
Weighted progress⁦1%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project482⁦2026-09-06⁩⁦2028-01-01⁩⁦1%⁩1.360.01—
1
Phase140⁦2026-09-06⁩⁦2027-01-24⁩⁦13%⁩0.110.01—
1.1
WBS element102⁦2026-09-06⁩⁦2026-12-17⁩⁦25%⁩0.050.010 / 1
1.2
WBS element61⁦2026-11-24⁩⁦2027-01-24⁩⁦0%⁩0.05—1 / 2
2
Phase99⁦2027-01-01⁩⁦2027-04-10⁩⁦0%⁩0.23——
2.1
WBS element61⁦2027-01-01⁩⁦2027-03-03⁩⁦0%⁩0.12—1 / 1
2.2
WBS element61⁦2027-02-08⁩⁦2027-04-10⁩⁦0%⁩0.12—1 / 2
3
Phase137⁦2027-03-18⁩⁦2027-08-02⁩⁦0%⁩0.54——
3.1
WBS element61⁦2027-03-18⁩⁦2027-05-18⁩⁦0%⁩0.18—1 / 1
3.2
WBS element61⁦2027-04-25⁩⁦2027-06-25⁩⁦0%⁩0.18—1 / 1
3.3
WBS element61⁦2027-06-02⁩⁦2027-08-02⁩⁦0%⁩0.18—1 / 2
4
Phase99⁦2027-07-10⁩⁦2027-10-17⁩⁦0%⁩0.27——
4.1
WBS element61⁦2027-07-10⁩⁦2027-09-09⁩⁦0%⁩0.14—1 / 1
4.2
WBS element61⁦2027-08-17⁩⁦2027-10-17⁩⁦0%⁩0.14—1 / 2
5
Phase99⁦2027-09-24⁩⁦2028-01-01⁩⁦0%⁩0.20——
5.1
WBS element61⁦2027-09-24⁩⁦2027-11-24⁩⁦0%⁩0.10—1 / 1
5.2
WBS element61⁦2027-11-01⁩⁦2028-01-01⁩⁦0%⁩0.10—1 / 1
Total⁦1%⁩1.360.01