PRJ-2026-028On track4ExecutionWaterfallIn progress

Operational Plans & Scorecards for the 2025–2030 Strategy

Add to watchlist

Turning the four pillars and their twelve objectives into department operational plans, OKRs and measurement cycles.

Budget (BAC)

SAR 160K

Actual cost

SAR 112K

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 160K

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
RC-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2025-10-05⁩
Hijri
13 Rabiʻ II 1447 AH
ApprovedDMD-2026-028Operational Plans & Scorecards for the 2025–2030 Strategy

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-028
Project
Operational Plans & Scorecards for the 2025–2030 Strategy
Portfolio
Institutional Excellence & Capability Portfolio
Sector
Strategy & Institutional Excellence
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Abeer H. Al-Shamrani

1The proposalAuto-filled

TitleAuto-filled
Operational Plans & Scorecards for the 2025–2030 Strategy
Proposed byAuto-filled
Abeer H. Al-Shamrani
DepartmentAuto-filled
Strategy Management
Submitted onAuto-filled
⁦2025-10-05⁩
Proposal numberAuto-filled
DMD-2026-028

2Justification

Turning the four pillars and their twelve objectives into department operational plans, OKRs and measurement cycles.

3Objectives

  1. Streamlined governance and dependable technology

Strategic objectives served

  • SO-4.2 — Streamlined governance and dependable technology

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 160K

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 115K
Supervision & consultingSAR 20K
Internal teamSAR 15K
Contingency reserve (5%)SAR 10K
TotalSAR 160K

6Initial risks

RiskLevelProposed response
No initial risks recorded

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Abeer H. Al-ShamraniHead of Strategy ManagementSubmitted—⁦2025-10-05⁩ 12:27
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2025-10-07⁩ 10:37
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-10-12⁩ 11:44
4Portfolio manager reviewTechnical acceptanceDr. Noura M. Al-OtaibiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2025-10-13⁩ 12:51
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-10-15⁩ 12:03
6Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2025-10-16⁩ 14:05

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2025-10-07⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2025-10-12⁩

Portfolio manager review

Dr. Noura M. Al-Otaibi

Approved⁦2025-10-13⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2025-10-15⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2025-10-16⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Abeer H. Al-Shamrani on ⁦2025-10-05⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2025-10-07⁩ at ⁦10:37⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-10-12⁩ at ⁦11:44⁩

  3. Technical acceptance

    Portfolio manager review

    Dr. Noura M. Al-Otaibi · Portfolio manager

    Approved · ⁦2025-10-13⁩ at ⁦12:51⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-10-15⁩ at ⁦12:03⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2025-10-16⁩ at ⁦14:05⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-10-26⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Abeer H. Al-Shamrani

  2. V1Returned for edit⁦2025-10-05⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Abeer H. Al-Shamrani