Operational Plans & Scorecards for the 2025–2030 Strategy
Add to watchlistTurning the four pillars and their twelve objectives into department operational plans, OKRs and measurement cycles.
Budget (BAC)
Actual cost
70% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure27 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-06-27 | 2026-07-12 | +15 days | Abeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-08-09 | 2026-09-04 | +26 days | Abeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-09-21 | 2026-10-26 | +35 days | Abeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-11-02 | 2026-11-22 | +20 days | Abeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.sa | On track | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-15 | 2026-12-15 | On time | Abeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
70%Awaiting acceptance
11%Not handed in
19%Deliverable flow
Display options
| Project plan & baseline028-D1 | 6% | CRT-028-01 | Approved | Abeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.sa | Dr. Amal F. Al-Sudairi | 2026-06-06 | V1 | 3 of 3 |
| Monitoring & reporting028-D2 | 6% | CRT-028-02 | Approved | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.sa | Dr. Amal F. Al-Sudairi | 2026-06-27 | V1 | 3 of 3 |
| Current-state assessment028-D3 | 12% | CRT-028-03 | Approved | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.sa | Dr. Amal F. Al-Sudairi | 2026-07-19 | V1 | 3 of 3 |
| Benchmarking028-D4 | 12% | CRT-028-04 | Approved | Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.sa | Dr. Amal F. Al-Sudairi | 2026-08-09 | V1 | 3 of 3 |
| Target model028-D5 | 17% | CRT-028-05 | Approved | Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.sa | Dr. Amal F. Al-Sudairi | 2026-08-30 | V1 | 3 of 3 |
| Roadmap028-D6 | 17% | CRT-028-06 | Approved | Abeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.sa | Dr. Amal F. Al-Sudairi | 2026-09-21 | V1 | 3 of 3 |
| Wave 1028-D7 | 11% | — | Under review | Abeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@chamber.sa | Dr. Amal F. Al-Sudairi | 2026-10-12 | V1 | 1 of 3 |
| Wave 2028-D8 | 11% | — | Draft | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.sa | Dr. Amal F. Al-Sudairi | 2026-11-02 | V0 | 0 of 3 |
| Knowledge transfer028-D9 | 4% | — | Draft | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.sa | Dr. Amal F. Al-Sudairi | 2026-11-24 | V0 | 0 of 3 |
| Final report028-D10 | 4% | — | Draft | Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.sa | Dr. Amal F. Al-Sudairi | 2026-12-15 | V0 | 0 of 3 |
| Total · 10 | 100% |