1.03Schedule performance index · 1.031.00Cost performance index · 1.00
Forecast finish
2026-12-15
On baseline
Execution·Stage 4 of 5
Next gate:Closure27 November 2026
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
0 days vs approved
Baseline (original = approved) · Current forecast2026-12-15
By earned schedule2027-01-23
Critical activities
1
of 6 open activities
Late activities
3
past their baseline finish
Schedule performance
0.83
earned ÷ planned value
Next milestone
in 25 days
Testing & acceptance complete
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2026
2027
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Today
2026-12-1570%
Operational Plans & Scorecards for the 2025–2030 StrategyPlanned: 2026-05-03 → 2026-12-15Forecast: 2026-05-03 → 2026-12-15Float: 0d