PRJ-2026-031On track5ClosureScrumCompleted

Certificate of Origin & e-Attestation Automation

Add to watchlist

Completed: certificates of origin, document attestation and verification fully online.

Budget (BAC)

SAR 410K

Actual cost

SAR 398K

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 398K

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work397.7K⁦16⁩ elements
Unallocated contingency12.3KSAR 21K
Budget at completion410KPRJ-2026-031
Weighted progress⁦100%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project469⁦2024-04-07⁩⁦2025-07-20⁩⁦100%⁩0.400.40—
1
Phase105⁦2024-04-07⁩⁦2024-07-21⁩⁦100%⁩0.030.03—
1.1
WBS element65⁦2024-04-07⁩⁦2024-06-11⁩⁦100%⁩0.020.020 / 1
1.2
WBS element65⁦2024-05-17⁩⁦2024-07-21⁩⁦100%⁩0.020.021 / 2
2
Phase105⁦2024-06-27⁩⁦2024-10-10⁩⁦100%⁩0.070.07—
2.1
WBS element65⁦2024-06-27⁩⁦2024-08-31⁩⁦100%⁩0.030.031 / 1
2.2
WBS element65⁦2024-08-06⁩⁦2024-10-10⁩⁦100%⁩0.030.031 / 2
3
Phase145⁦2024-09-16⁩⁦2025-02-08⁩⁦100%⁩0.160.16—
3.1
WBS element64⁦2024-09-16⁩⁦2024-11-19⁩⁦100%⁩0.050.051 / 1
3.2
WBS element65⁦2024-10-26⁩⁦2024-12-30⁩⁦100%⁩0.050.051 / 1
3.3
WBS element64⁦2024-12-06⁩⁦2025-02-08⁩⁦100%⁩0.050.051 / 2
4
Phase105⁦2025-01-15⁩⁦2025-04-30⁩⁦100%⁩0.080.08—
4.1
WBS element65⁦2025-01-15⁩⁦2025-03-21⁩⁦100%⁩0.040.041 / 1
4.2
WBS element65⁦2025-02-24⁩⁦2025-04-30⁩⁦100%⁩0.040.041 / 2
5
Phase105⁦2025-04-06⁩⁦2025-07-20⁩⁦100%⁩0.060.06—
5.1
WBS element65⁦2025-04-06⁩⁦2025-06-10⁩⁦100%⁩0.030.031 / 1
5.2
WBS element65⁦2025-05-16⁩⁦2025-07-20⁩⁦100%⁩0.030.031 / 1
Total⁦100%⁩0.400.40