PRJ-2026-008On track4ExecutionScrumIn progress

Dispute Settlement & Commercial Arbitration Platform — Release 2

Add to watchlist

Online filing of amicable-settlement and arbitration requests between businesses, the roster of accredited arbitrators and conciliators, and remote settlement sessions and their records.

Budget (BAC)

SAR 920K

Actual cost

SAR 821K

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 902K

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

4Achieved
1On track
0At risk
0Late
Average delay33 days
Oct 25Jan 26Apr 26Jul 26Oct 26
Contractual
Build completePlanned: ⁦2026-05-16⁩Forecast / actual: ⁦2026-07-07⁩Delay: 52 daysG3 +52
Executive
Project plan approvedPlanned: ⁦2025-09-10⁩Forecast / actual: ⁦2025-09-28⁩Delay: 18 daysG1 +18
Payment
Final handoverPlanned: ⁦2026-11-30⁩Forecast / actual: ⁦2026-11-30⁩G5
Regulatory
Testing & acceptance completePlanned: ⁦2026-08-23⁩Forecast / actual: ⁦2026-10-26⁩Delay: 64 daysG4 +64
Project
Designs approvedPlanned: ⁦2025-12-18⁩Forecast / actual: ⁦2026-01-19⁩Delay: 32 daysG2 +32

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-09-10⁩⁦2025-09-28⁩⁦+18⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.saAchieved1Approved
Designs approvedMS-G2Project⁦2025-12-18⁩⁦2026-01-19⁩⁦+32⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-05-16⁩⁦2026-07-07⁩⁦+52⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-08-23⁩⁦2026-10-26⁩⁦+64⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.saAchieved1Approved
Final handoverMS-G5Payment⁦2026-11-30⁩⁦2026-11-30⁩On timeKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.saOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦91%⁩

Awaiting acceptance

⁦5%⁩

Not handed in

⁦4%⁩

Deliverable flow

Pick a stage to filter the register
⁦11⁩ results
Export CSV
Project plan & baseline008-D1⁦5%⁩CRT-008-01ApprovedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.saDr. Lina S. Al-Hazzani⁦2025-07-22⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting008-D2⁦4%⁩CRT-008-02ApprovedDr. Lina S. Al-HazzaniDr. Lina S. Al-HazzaniExecutive Director, Legal Affairs & Board SecretaryP-052l.alhazzani@chamber.saDr. Lina S. Al-Hazzani⁦2025-09-10⁩V1⁦3⁩ of ⁦3⁩
Business requirements008-D3⁦9%⁩CRT-008-03ApprovedDr. Lina S. Al-HazzaniDr. Lina S. Al-HazzaniExecutive Director, Legal Affairs & Board SecretaryP-052l.alhazzani@chamber.saDr. Lina S. Al-Hazzani⁦2025-10-29⁩V1⁦3⁩ of ⁦3⁩
Solution design008-D4⁦9%⁩CRT-008-04ApprovedEng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.saDr. Lina S. Al-Hazzani⁦2025-12-18⁩V1⁦3⁩ of ⁦3⁩
Release 1008-D5⁦14%⁩CRT-008-05ApprovedEng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.saDr. Lina S. Al-Hazzani⁦2026-02-06⁩V1⁦3⁩ of ⁦3⁩
Release 2008-D6⁦14%⁩CRT-008-06ApprovedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.saDr. Lina S. Al-Hazzani⁦2026-03-27⁩V1⁦3⁩ of ⁦3⁩
Integrations008-D7⁦14%⁩CRT-008-07ApprovedDr. Lina S. Al-HazzaniDr. Lina S. Al-HazzaniExecutive Director, Legal Affairs & Board SecretaryP-052l.alhazzani@chamber.saDr. Lina S. Al-Hazzani⁦2026-05-16⁩V1⁦3⁩ of ⁦3⁩
System testing008-D8⁦11%⁩CRT-008-08ApprovedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.saDr. Lina S. Al-Hazzani⁦2026-07-04⁩V1⁦3⁩ of ⁦3⁩
User acceptance testing008-D9⁦11%⁩CRT-008-09ApprovedDr. Lina S. Al-HazzaniDr. Lina S. Al-HazzaniExecutive Director, Legal Affairs & Board SecretaryP-052l.alhazzani@chamber.saDr. Lina S. Al-Hazzani⁦2026-08-23⁩V1⁦3⁩ of ⁦3⁩
Training & change008-D10⁦5%⁩—Under reviewDr. Lina S. Al-HazzaniDr. Lina S. Al-HazzaniExecutive Director, Legal Affairs & Board SecretaryP-052l.alhazzani@chamber.saDr. Lina S. Al-Hazzani⁦2026-10-11⁩V1⁦1⁩ of ⁦3⁩
Go-live & handover008-D11⁦4%⁩—DraftEng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.saDr. Lina S. Al-Hazzani⁦2026-11-30⁩V0⁦0⁩ of ⁦3⁩
Total · 11⁦100%⁩
⁦1⁩–⁦11⁩ of ⁦11⁩