Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-012On track4ExecutionAgileIn progress

Institutional Performance Measurement & Power BI Dashboards

Add to watchlist

The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.

Budget (BAC)

SAR 490K

Actual cost

SAR 372K

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 490K

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Institutional Performance Measurement & Power BI Dashboards

PRJ-2026-012 · Strategy & Institutional Excellence · Operational · WP-2025-012

In progressOn track4ExecutionProject manager: Tariq S. Al-Yami · Sponsor: Dr. Mohammed I. Al-Subaie
Progress
⁦76%⁩ / ⁦75%⁩
SPI · CPI
1.01 · 1.00
Spend
SAR 372K / SAR 490K
Estimate at completion
SAR 490K

Schedule

⁦1%⁩ ahead⁦76%⁩

Planned to date ⁦75%⁩

Forecast finish: 2026-12-2415 Rajab 1448 AH · On time

SPI1.01Schedule performance index · 1.01CPI1.00Cost performance index · 1.00

Health dimensions

On track

Last update: 2026-10-2716 Jumada I 1448 AH · Up to date

Deliverables

⁦6⁩ of ⁦8⁩ due deliverables accepted on time (⁦75%⁩)

Next milestones

  • Testing & acceptance complete2027-01-0325 Rajab 1448 AH
  • Final handover2027-01-2315 Shaʻban 1448 AH

Top risks

  • None

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 0.5M: 1 on track and 0 red or critical. Weighted progress is 76% against 75% planned, spend SAR 0.4M, and EAC SAR 0.5M (SAR 0M under).

No project is more than a month behind baseline.

Riyadh Chamber of Commerce & Industry · prepared by Tariq S. Al-Yami in MunjazInternal

Status: On track ·Project page

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close