PRJ-2026-012On track4ExecutionAgileIn progress

Institutional Performance Measurement & Power BI Dashboards

Add to watchlist

The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.

Budget (BAC)

SAR 490K

Actual cost

SAR 372K

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 490K

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

3Achieved
0On track
1At risk
1Late
Average delay49 days
Jan 26Apr 26Jul 26Oct 26Jan 27
Contractual
Build completePlanned: ⁦2026-07-03⁩Forecast / actual: ⁦2026-09-03⁩Delay: 62 daysG3 +62
Executive
Project plan approvedPlanned: ⁦2026-01-03⁩Forecast / actual: ⁦2026-01-27⁩Delay: 24 daysG1 +24
Payment
Final handoverPlanned: ⁦2026-12-31⁩Forecast / actual: ⁦2027-01-23⁩Delay: 23 daysG5 +23
Regulatory
Testing & acceptance completePlanned: ⁦2026-10-01⁩Forecast / actual: ⁦2027-01-03⁩Delay: 94 daysG4 +94
Project
Designs approvedPlanned: ⁦2026-04-03⁩Forecast / actual: ⁦2026-05-17⁩Delay: 44 daysG2 +44

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-01-03⁩⁦2026-01-27⁩⁦+24⁩ daysTariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.saAchieved1Approved
Designs approvedMS-G2Project⁦2026-04-03⁩⁦2026-05-17⁩⁦+44⁩ daysTariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-07-03⁩⁦2026-09-03⁩⁦+62⁩ daysTariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-10-01⁩⁦2027-01-03⁩⁦+94⁩ daysTariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.saLate0Not requested
Final handoverMS-G5Payment⁦2026-12-31⁩⁦2027-01-23⁩⁦+23⁩ daysTariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.saAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦76%⁩

Awaiting acceptance

⁦14%⁩

Not handed in

⁦10%⁩

Deliverable flow

Pick a stage to filter the register
⁦10⁩ results
Export CSV
Project plan & baseline012-D1⁦5%⁩CRT-012-01ApprovedTariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.saDr. Amal F. Al-Sudairi⁦2025-11-18⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting012-D2⁦5%⁩CRT-012-02ApprovedDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.saDr. Amal F. Al-Sudairi⁦2026-01-03⁩V1⁦3⁩ of ⁦3⁩
Current-state assessment012-D3⁦10%⁩CRT-012-03ApprovedDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.saDr. Amal F. Al-Sudairi⁦2026-02-17⁩V1⁦3⁩ of ⁦3⁩
Benchmarking012-D4⁦10%⁩CRT-012-04ApprovedDr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.saDr. Amal F. Al-Sudairi⁦2026-04-03⁩V1⁦3⁩ of ⁦3⁩
Target model012-D5⁦16%⁩CRT-012-05ApprovedDr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.saDr. Amal F. Al-Sudairi⁦2026-05-19⁩V1⁦3⁩ of ⁦3⁩
Roadmap012-D6⁦15%⁩CRT-012-06ApprovedTariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.saDr. Amal F. Al-Sudairi⁦2026-07-03⁩V1⁦3⁩ of ⁦3⁩
Wave 1012-D7⁦15%⁩CRT-012-07ApprovedTariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.saDr. Amal F. Al-Sudairi⁦2026-08-17⁩V1⁦3⁩ of ⁦3⁩
Wave 2012-D8⁦14%⁩—SubmittedDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.saDr. Amal F. Al-Sudairi⁦2026-10-01⁩V1⁦1⁩ of ⁦3⁩
Knowledge transfer012-D9⁦5%⁩—DraftDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.saDr. Amal F. Al-Sudairi⁦2026-11-16⁩V0⁦0⁩ of ⁦3⁩
Final report012-D10⁦5%⁩—DraftDr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.saDr. Amal F. Al-Sudairi⁦2026-12-31⁩V0⁦0⁩ of ⁦3⁩
Total · 10⁦100%⁩
⁦1⁩–⁦10⁩ of ⁦10⁩