PRJ-2026-012On track4ExecutionAgileIn progress

Institutional Performance Measurement & Power BI Dashboards

Add to watchlist

The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.

Budget (BAC)

SAR 490K

Actual cost

SAR 372K

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 490K

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work475.3K⁦15⁩ elements
Unallocated contingency14.7KSAR 25K
Budget at completion490KPRJ-2026-012
Weighted progress⁦76%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project503⁦2025-09-07⁩⁦2027-01-23⁩⁦76%⁩0.480.37—
1
Phase142⁦2025-09-07⁩⁦2026-01-27⁩⁦100%⁩0.050.05—
1.1
WBS element88⁦2025-09-07⁩⁦2025-12-04⁩⁦100%⁩0.020.020 / 1
1.2
WBS element87⁦2025-11-01⁩⁦2026-01-27⁩⁦100%⁩0.020.021 / 2
2
Phase142⁦2025-12-26⁩⁦2026-05-17⁩⁦100%⁩0.100.10—
2.1
WBS element87⁦2025-12-26⁩⁦2026-03-23⁩⁦100%⁩0.050.051 / 1
2.2
WBS element88⁦2026-02-18⁩⁦2026-05-17⁩⁦100%⁩0.050.051 / 2
3
Phase142⁦2026-04-14⁩⁦2026-09-03⁩⁦100%⁩0.140.15—
3.1
WBS element88⁦2026-04-14⁩⁦2026-07-11⁩⁦100%⁩0.070.071 / 1
3.2
WBS element87⁦2026-06-08⁩⁦2026-09-03⁩⁦100%⁩0.070.071 / 2
4
Phase166⁦2026-07-21⁩⁦2027-01-03⁩⁦54%⁩0.140.08—
4.1
WBS element85⁦2026-08-02⁩⁦2026-10-26⁩⁦100%⁩0.070.071 / 1
4.2
WBS element166⁦2026-07-21⁩⁦2027-01-03⁩⁦7%⁩0.070.011 / 2
5
Phase26⁦2026-12-28⁩⁦2027-01-23⁩⁦0%⁩0.05——
5.1
WBS element16⁦2026-12-28⁩⁦2027-01-13⁩⁦0%⁩0.02—1 / 1
5.2
WBS element16⁦2027-01-07⁩⁦2027-01-23⁩⁦0%⁩0.02—1 / 1
Total⁦76%⁩0.480.37