PRJ-2026-013At risk4ExecutionConstructionIn progress

Smart Access, Visitor & Event Management at HQ & the Branches

Add to watchlist

1,200 cameras and gates and QR check-in for events at headquarters and the branches, with a central monitoring room, starting with the conference hall at the current headquarters.

Early warning: ⁦58%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 3.7M

Actual cost

SAR 3.1M

⁦84%⁩ of budget

Progress

⁦79%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SAR 3.9M

SAR +236K

SPI · CPI

0.88Schedule performance index · 0.880.94Cost performance index · 0.94

Forecast finish

⁦2026-12-15⁩

45 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure11 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
RC-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2024-07-21⁩
Hijri
15 Muharram 1446 AH
ApprovedDMD-2026-013Smart Access, Visitor & Event Management at HQ & the Branches

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-013
Project
Smart Access, Visitor & Event Management at HQ & the Branches
Portfolio
New Headquarters & Investment Assets Portfolio
Sector
Support Services Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Waleed O. Al-Juhani

1The proposalAuto-filled

TitleAuto-filled
Smart Access, Visitor & Event Management at HQ & the Branches
Proposed byAuto-filled
Eng. Waleed O. Al-Juhani
DepartmentAuto-filled
Facilities Operations & Maintenance Department
Submitted onAuto-filled
⁦2024-07-21⁩
Proposal numberAuto-filled
DMD-2026-013

2Justification

1,200 cameras and gates and QR check-in for events at headquarters and the branches, with a central monitoring room, starting with the conference hall at the current headquarters.

3Objectives

  1. A stronger presence in forums, events and trade delegations
  2. A better member experience and service quality

Strategic objectives served

  • SO-3.2 — A stronger presence in forums, events and trade delegations
  • SO-2.2 — A better member experience and service quality

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 3.7M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 2.7M
Supervision & consultingSAR 515K
Internal teamSAR 335K
Contingency reserve (5%)SAR 185K
TotalSAR 3.7M

6Initial risks

RiskLevelProposed response
Camera and gate quantity variances between drawings and siteMediumTreated in the risk management plan
Late integration of the central monitoring room with building systemsMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceSubmitted—⁦2024-07-21⁩ 12:15
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2024-07-23⁩ 10:25
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-07-28⁩ 11:32
4Portfolio manager reviewTechnical acceptanceEng. Bandar M. Al-ShammariPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2024-07-29⁩ 12:39
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-07-31⁩ 12:51
6Project Approval CommitteeTechnical acceptanceApproval engineProject Approval CommitteePre-breach alert—⁦2024-08-06⁩ 08:00
7Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2024-08-07⁩ 14:53

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2024-07-23⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2024-07-28⁩

Portfolio manager review

Eng. Bandar M. Al-Shammari

Approved⁦2024-07-29⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2024-07-31⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2024-08-07⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Waleed O. Al-Juhani on ⁦2024-07-21⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2024-07-23⁩ at ⁦10:25⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-07-28⁩ at ⁦11:32⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Bandar M. Al-Shammari · Portfolio manager

    Approved · ⁦2024-07-29⁩ at ⁦12:39⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-07-31⁩ at ⁦12:51⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2024-08-07⁩ at ⁦14:53⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-08-11⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Waleed O. Al-Juhani

  2. V1Returned for edit⁦2024-07-21⁩

    First draft — returned to complete the cost and risks