Add to watchlist
1,200 cameras and gates and QR check-in for events at headquarters and the branches, with a central monitoring room, starting with the conference hall at the current headquarters.
Early warning: 58% chance of slipping within 45 days
Budget (BAC)
SAR 3.7M
Actual cost
SAR 3.1M
84% of budget
Progress
79%Awaiting acceptance 9%
Estimate at completion
SAR 3.9M
SAR +236K
SPI · CPI
0.88Schedule performance index · 0.880.94Cost performance index · 0.94
Forecast finish
2026-12-15
45 days behind baseline
Execution·Stage 4 of 5
Next gate:Closure11 September 2026
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+72 days vs approved
Baseline (original = approved)2026-10-31
Current forecast2027-01-11
By earned schedule2027-07-18
Critical activities
4
of 5 open activities
Late activities
3
past their baseline finish
Schedule performance
0.79
earned ÷ planned value
Next milestone
in 55 days
Testing & acceptance complete
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2025
2026
2027
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
Today
2027-01-1179%
Smart Access, Visitor & Event Management at HQ & the BranchesPlanned: 2025-02-16 → 2026-10-31Forecast: 2025-02-16 → 2027-01-11Float: 0d