Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-016At risk4ExecutionWaterfallIn progress

Business Observatory & Data Governance

Add to watchlist

Business indicators for the Riyadh Region on the observatory portal, and governance of member and business data under the National Data Management Office policies.

Budget (BAC)

SAR 1.1M

Actual cost

SAR 702K

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 1.1M

SAR +57K

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Business Observatory & Data Governance

PRJ-2026-016 · Business Support Sector · Strategic · WP-2025-016

In progressAt risk4ExecutionProject manager: Rahaf I. Al-Nefaie · Sponsor: Eng. Majed S. Al-Rasheed
Progress
⁦62%⁩ / ⁦70%⁩
SPI · CPI
0.89 · 0.95
Spend
SAR 702K / SAR 1.1M
Estimate at completion
SAR 1.1M

Schedule

⁦8%⁩ behind⁦62%⁩

Planned to date ⁦70%⁩

Forecast finish: 2027-01-1810 Shaʻban 1448 AH · 18 days late

SPI0.89Schedule performance index · 0.89CPI0.95Cost performance index · 0.95

Health dimensions

At risk

Last update: 2026-10-2110 Jumada I 1448 AH · Up to date

Deliverables

⁦5⁩ of ⁦9⁩ due deliverables accepted on time (⁦56%⁩)

Next milestones

  • Build complete2026-11-133 Jumada II 1448 AH
  • Testing & acceptance complete2026-12-156 Rajab 1448 AH
  • Final handover2027-01-168 Shaʻban 1448 AH

Top risks

  • Too few accredited data owners in the sectors and departments9

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 1.1M: 0 on track and 0 red or critical. Weighted progress is 62% against 70% planned, spend SAR 0.7M, and EAC SAR 1.1M (SAR 0.1M over).

No project is more than a month behind baseline.

Riyadh Chamber of Commerce & Industry · prepared by Rahaf I. Al-Nefaie in MunjazInternal

Status: At risk ·Project page

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close