PRJ-2026-024On track1Pre-startStage-GatePlanned

Unified Contact Centre 920004565 & AI Assistant

Add to watchlist

A multichannel contact centre on the unified number and an Arabic AI assistant on the website, the app and WhatsApp answering members’ questions — part of the Year of AI 2026.

Budget (BAC)

SAR 5.5M

Actual cost

SAR 0

⁦0%⁩ of budget

Progress

⁦0%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 5.5M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

Pre-startStage ⁦1⁩ of ⁦5⁩

Next gate:Initiation4 November 2026

  1. Pre-start · Current stagePre-start · Current stage
  2. Gate into «Initiation»DecisionNot held yetDate4 November 2026Initiation · Not startedInitiation · Not started
  3. Gate into «Planning»DecisionNot held yetPlanning · Not startedPlanning · Not started
  4. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work5.3M⁦16⁩ elements
Unallocated contingency165KSAR 275K
Budget at completion5.5MPRJ-2026-024
Weighted progress⁦0%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project846⁦2027-01-03⁩⁦2029-04-28⁩⁦0%⁩5.34——
1
Phase189⁦2027-01-03⁩⁦2027-07-11⁩⁦0%⁩0.43——
1.1
WBS element116⁦2027-01-03⁩⁦2027-04-29⁩⁦0%⁩0.21—0 / 1
1.2
WBS element116⁦2027-03-17⁩⁦2027-07-11⁩⁦0%⁩0.21—1 / 2
2
Phase189⁦2027-05-29⁩⁦2027-12-04⁩⁦0%⁩0.91——
2.1
WBS element116⁦2027-05-29⁩⁦2027-09-22⁩⁦0%⁩0.45—1 / 1
2.2
WBS element116⁦2027-08-10⁩⁦2027-12-04⁩⁦0%⁩0.45—1 / 2
3
Phase262⁦2027-10-22⁩⁦2028-07-10⁩⁦0%⁩2.13——
3.1
WBS element116⁦2027-10-22⁩⁦2028-02-15⁩⁦0%⁩0.71—1 / 1
3.2
WBS element116⁦2028-01-03⁩⁦2028-04-28⁩⁦0%⁩0.71—1 / 1
3.3
WBS element116⁦2028-03-16⁩⁦2028-07-10⁩⁦0%⁩0.71—1 / 2
4
Phase189⁦2028-05-28⁩⁦2028-12-03⁩⁦0%⁩1.07——
4.1
WBS element116⁦2028-05-28⁩⁦2028-09-21⁩⁦0%⁩0.53—1 / 1
4.2
WBS element116⁦2028-08-09⁩⁦2028-12-03⁩⁦0%⁩0.53—1 / 2
5
Phase189⁦2028-10-21⁩⁦2029-04-28⁩⁦0%⁩0.80——
5.1
WBS element116⁦2028-10-21⁩⁦2029-02-14⁩⁦0%⁩0.40—1 / 1
5.2
WBS element116⁦2029-01-02⁩⁦2029-04-28⁩⁦0%⁩0.40—1 / 1
Total⁦0%⁩5.340.00