PRJ-2026-028On track4ExecutionWaterfallIn progress

Operational Plans & Scorecards for the 2025–2030 Strategy

Add to watchlist

Turning the four pillars and their twelve objectives into department operational plans, OKRs and measurement cycles.

Budget (BAC)

SAR 160K

Actual cost

SAR 112K

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 160K

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Project weight

The weight and the relative weight in the portfolio

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Approval

Project weight

The weight and the relative weight in the portfolio

Form no.
RC-PMO-F03
Template edition
1.0
Version
V2
Form date
⁦2026-09-16⁩
Hijri
5 Rabiʻ II 1448 AH
ApprovedPRJ-2026-028Operational Plans & Scorecards for the 2025–2030 Strategy

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-028
Project
Operational Plans & Scorecards for the 2025–2030 Strategy
Portfolio
Institutional Excellence & Capability Portfolio
Sector
Strategy & Institutional Excellence
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Abeer H. Al-Shamrani

1Weight and relative weightAuto-filled

Project weight score

65 of 100

Relative weight in the portfolio

⁦23.8%⁩

Portfolio

Institutional Excellence & Capability Portfolio

5 projects

Its share of the portfolio’s progress

16.7 points of 61.9%

2Weight criteriaAuto-filled

Each criterion is rated 1–5 from the project’s record and multiplied by its approved weight.

CriterionRated fromWeightRatingPoints
Strategic importanceThe project’s strategic value⁦35%⁩428.0
Budget sizeApproved budget (BAC)⁦25%⁩15.0
Impact on members & beneficiariesThe project’s alignment score⁦20%⁩520.0
Complexity & riskThe project’s risk score⁦10%⁩12.0
Project classificationThe project’s classification⁦10%⁩510.0
Weight score—⁦100%⁩—65

3Relative weights across the portfolioAuto-filled

Proposed and cancelled projects are left out; suspended ones keep their frozen progress.

ProjectScoreRelative weightProgress
Operational Plans & Scorecards for the 2025–2030 Strategy65⁦23.8%⁩⁦70%⁩
Entrepreneurship Fast Track Platform56⁦20.5%⁩⁦63%⁩
Training Centre e-Learning Platform54⁦19.8%⁩⁦4%⁩
Institutional Performance Measurement & Power BI Dashboards50⁦18.3%⁩⁦76%⁩
Enterprise Risk & Business Continuity Framework48⁦17.6%⁩⁦100%⁩
Weighted portfolio progress—⁦100%⁩⁦61.9%⁩

Approval logChain: Project weight approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleSubmitted—⁦2026-09-16⁩ 12:09
2Weight model complianceMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-09-20⁩ 14:23
3Portfolio manager approvalTechnical acceptanceDr. Noura M. Al-OtaibiPortfolio managerApproved—⁦2026-09-21⁩ 09:30

Signatures

Weight model compliance

Ghada A. Al-Shahrani

Approved⁦2026-09-20⁩

Portfolio manager approval

Dr. Noura M. Al-Otaibi

Approved⁦2026-09-21⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F03 · version V2

Project weight

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project weight approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2026-09-16⁩

  1. Methodology review

    Weight model compliance

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-09-20⁩ at ⁦14:23⁩

  2. Technical acceptance

    Portfolio manager approval

    Dr. Noura M. Al-Otaibi · Portfolio manager

    Approved · ⁦2026-09-21⁩ at ⁦09:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-09-14⁩

    Classification added at 10; budget cut from 35 to 25 so the building projects do not swamp the portfolio

    Dr. Noura M. Al-Otaibi

  2. V1Approved⁦2025-12-02⁩

    First model: strategic importance, budget, impact, complexity